The View Time-Distance Diagram command lets you initiate a time-distance diagram with the selected relay group as the starting point of the diagram. .
TO DISPLAY A TIME-DISTANCE DIAGRAM
1. Highlight a relay group that contains one or more overcurrent relays, distance relays, fuses or reclosers.
The symbol of the selected relay group will turn red.
2. Select the Relay | Display Time-Distance Window command.
The Time-Distance Window will open showing a path of transmission lines and closed switches that start with the selected relay location. The path starts with the branch where the selected relay group resides and ends when the program encounter a junction node that is connected to three or more transmission lines or closed switches.
OneLiner will automatically close the OC Curves Window and the DS Relays Window if they are open.
See Section 3.5 for more information on the commands available in the Time-Distance Window.
Main Window
RELAY MENU