The In/Out Of Service | Put In Service command in the Main Window lets you put back in service a piece of equipment that was previously taken out of service. This command, when applied to a bus, will put all of the attached equipment in service. To execute this command you must first select a piece of equipment.
TO PUT A PIECE OF EQUIPMENT BACK IN SERVICE:
1. Select a branch, generator load, shunt or bus.
Click the left button once on the symbol of the piece of equipment you want to put back in service.
The symbol will turn dotted red when selected.
2. Select the Network | In/Out Of Service | Put In Service command.
Note: The menu item will be dimmed and cannot be activated if the equipment selected had not previously been taken out of service.
The selected equipment will be put back in service. If you have selected a bus in step 1 above, all attached equipment will be put back in service. The symbol(s) will be drawn in its normal style and color.